[#14902] All day events extended by one day upon modifying start date
Summary All day events extended by one day upon modifying start date
Queue Kronolith
Queue Version Git master
Type Bug
State Unconfirmed
Priority 1. Low
Owners
Requester build+horde (at) de-korte (dot) org
Created 02/25/2019 (2270 days ago)
Due
Updated 02/25/2019 (2270 days ago)
Assigned
Resolved
Milestone
Patch No

History
02/25/2019 10:22:56 AM build+horde (at) de-korte (dot) org Comment #1
State ⇒ Unconfirmed
Priority ⇒ 1. Low
Type ⇒ Bug
Summary ⇒ All day events extended by one day upon modifying start date
Queue ⇒ Kronolith
Milestone ⇒
Patch ⇒ No
Reply to this comment
When an al day event is copied into a new event, the duration is 
extended by one day.

Example: create an all day event for one day. After saving, open the 
event, change the start date to the next day. Notice that the end day 
will change not to the next day, but the day after that. So now the 
event which was initially a one day event, has become two days.

This can also be demonstrated on demo.horde.org, so it is not 
something local to my installation.